Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

In delhi Sultanate who was called wise fool king, I know answer i am testing others iq let's see​
I need help with this please help me i got it wrong
The permiter of the red square is 36 inches. Use this information to determine the area of the red square.
The splitting apart of an atom's nucleus is called Fizzing Fission Fusion Atomic
Which of the following describes the MAIN thematic concept in the passage?
No quiere borrar la página. La quiere ___________. ​ Question 12 options: ​regresar ​guardar
The ratio of the number of boys to the number of girls in a certain class is 8:5. if the number of boys in that class is 52 students . find the number of girls?
12. The ability of Carbon to form up to 4 bonds is important to living organisms in that it allows Carbon to A. bond only with Hydrogen and Oxygen. B. decay int
Doug had 7 bags of sugar his daughter used 2 and 3/8 of the sugar how much sugar is left
PLEASE HELP ME WITH QUESTIONS 2-3 IM GIVING 18 POINTS AWAY AND EXPLAIN YOUR ANSWER PLEASE